simple_temporal_networks
This library provides the stn_protocol protocol and the stn
object for Simple Temporal Networks (STNs). It is a metric substrate for
temporal reasoning, e.g., Temporal ATMS libraries. It reuses the
intervals library for concrete Allen relation views.
States are opaque ground terms. Updates return a new state without
changing the original, allowing independent networks and branching
histories. All successfully returned states are consistent. Time-point
labels are distinct ground terms, compared by term identity; for
example, 1 and 1.0 name different time-points. The reference
label zero is reserved and denotes time zero. It is added
automatically and must not be supplied to new/2.
API documentation
Open the ../../apis/library_index.html#simple-temporal-networks link in a web browser.
Loading
To load this library, load its loader.lgt file:
| ?- logtalk_load(simple_temporal_networks(loader)).
Testing
To test this library, load its tester.lgt file:
| ?- logtalk_load(simple_temporal_networks(tester)).
Metric model
An input constraint(X, Y, Delta) denotes:
time(Y) - time(X) =< Delta
Delta must be a finite integer or float. A directed edge from X to Y
therefore supplies an upper difference bound, not an earliest time.
Shortest-path distance d(X,Y) is the tightest upper bound on Y - X.
For consistent networks:
difference_bounds(X,Y) = [-d(Y,X), d(X,Y)]
earliest(T) = -d(T,zero)
latest(T) = d(zero,T)
There is no implicit assumption that non-reference time-points are
non-negative. Missing directed paths yield the symbolic bound
positive_infinity; negating that bound yields negative_infinity.
These atoms are not arithmetic values and must not be passed to
is/2. Self-distances and both bounds of zero are zero. A
consistent network may have one-sided or fully unbounded windows.
Bellman-Ford with initially zero potentials for every node detects
negative cycles, including components disconnected from zero. A
consistent graph is then closed using Floyd-Warshall with fresh matrices
for successive intermediate nodes. No destructive term updates are used.
API overview
Public modes, argument names, failure conditions, and explanation
formats are documented in stn_protocol.lgt using mode/2 and
info/2 directives.
new/2,add_time_points/3: Construct a network or append fresh time-pointsremove_time_points/3: Remove time-points and all incident source constraints, rebuilding oncetime_points/2,constraints/2,consistent/1: Inspect a library-created stateschedule/2: Return one finite feasible time assignmentearliest_schedule/2: Return the componentwise earliest assignment when all lower bounds are finiteadd_constraint/5-6: Add one upper difference bound, optionally returning its IDadd_constraints/3-4: Atomically add a batch, optionally returning its IDstry_add_constraints/4: Return an updated state or an identified negative-cycle witnessremove_constraints/3: Remove source constraints by ID and rebuild oncedistance/4-5: Query an upper difference bound, optionally with one supporting pathearliest/3,latest/3,bounds/4: Query absolute time boundsdifference_bounds/5: Query both relative difference boundsentails/4-5: Test an upper difference bound, optionally with a supporting pathcan_precede/3,must_precede/3: Test possible or entailed strict precedencecan_precede_or_equal/3,must_precede_or_equal/3: Test possible or entailed non-strict precedencewindow_interval/3: Export a finite non-degenerate marginal window as numerici(Start,End)event_interval/4: Export a fixed positive-duration event as numerici(Start,End)window_relation/4: Classify finite non-degenerate marginal windowsevent_relation/6: Classify two events whose four endpoints are fixed
Malformed public arguments, unknown time-point labels, and invalid weights fail without binding input variables. State arguments must be states returned by this API. Arithmetic evaluation and representation errors propagate rather than being interpreted as temporal contradictions. Empty update batches and empty time-point extensions return the original state. Retraction accepts a list of positive integer IDs, ignoring missing IDs and duplicate requests.
remove_time_points/3 accepts a ground list of labels and removes
those points together with every source constraint whose endpoint is
removed. Missing labels and duplicate requests are ignored; a request
containing zero fails atomically. Requests removing no existing
point return the original state, while isolated points are removed even
when no source changes. Surviving node/source order, source IDs, and the
next source ID are preserved. Queries for removed points fail because
those labels are no longer declared.
Schedules
schedule(STN, Schedule) returns one finite assignment as
time(Point, Value) terms in declaration order, including
time(zero, 0) first. It also assigns finite values to isolated
points, disconnected components, and points with unbounded absolute
windows. The original state and source identifiers are unchanged.
Repeated calls on the same state select the same assignment.
The assignment uses each cached closure column’s minimum finite
distance, then shifts all values so the reference point is zero. In
exact arithmetic, these minima are shortest-path potentials from an
implicit source with zero-weight edges to every point. Normalization
preserves their differences. Every retained source inequality is checked
after normalization using backend arithmetic. A violation raises
evaluation_error(stn_numerical_inconsistency); non-finite arithmetic
raises evaluation_error(float_overflow). No tolerance or numerical
repair is applied, and floating-point results remain approximate.
This selects one assignment, not an enumeration, optimization, execution policy, or necessarily a non-negative or globally earliest schedule. An unconstrained point need not receive zero when another component anchors the reference normalization. See the schedule and numeric limitations below.
earliest_schedule(STN, Schedule) instead returns each point’s finite
earliest absolute bound in the same format and declaration order, with
time(zero, 0) first. Every declared point must have a finite lower
bound; finite upper bounds are not required. An unbounded lower bound
causes failure without binding the output. No artificial floor is added,
and the state and source identifiers are unchanged.
This reads the reference column of the cached closure and negates each
distance to zero. In exact arithmetic, the resulting assignment
jointly attains every coordinate’s minimum, including bounds propagated
through correlated points. It uses the same retained-source validation
as schedule/2; floating-point feasibility and minimality are not
exact-real guarantees.
For example, propagate a lower bound through a duration constraint while choosing the earliest value of an independently anchored point:
| ?- stn::new([a,b,c], STN0),
stn::add_constraints(STN0, [
constraint(a,zero,-5), constraint(b,a,-2),
constraint(c,zero,-1), constraint(zero,c,3)
], STN),
stn::earliest_schedule(STN, Schedule).
Schedule = [time(zero,0),time(a,5),time(b,7),time(c,1)].
Sources and explanations
Every accepted source receives a monotonically allocated positive
integer ID. constraints/2 returns constraint(Id,X,Y,Delta) terms
in insertion order, including parallel, redundant, and equal-weight
constraints. Synthetic zero diagonals are not source constraints.
Removing a stronger source can therefore restore a surviving weaker
bound or a tied alternative support. Removed IDs are not reused in
accepted descendant states.
Time-point deletion rebuilds from surviving source constraints, not from
cached implied distances. Bounds supported through a removed point can
therefore become weaker or unbounded. This is source retraction, not
variable elimination preserving the original network’s consequences on
surviving points. Re-adding a deleted label with add_time_points/3
creates an unconstrained point; its former incident sources are not
restored.
try_add_constraints(STN0, Constraints, Ids, Outcome) returns either:
consistent(STN)
inconsistent(cycle(Sources, TotalWeight))
Ids corresponds to the candidate batch in input order, even when
rejected. The cycle’s identified source constraints form an ordered
closed directed path with negative total weight. It can contain both
existing sources and candidate sources. The original state is unchanged
in either case. The consistent-only insertion predicates fail for the
inconsistent outcome.
distance(STN,X,Y,Upper,Path) returns one ordered source-constraint
path supporting a finite distance. It fails when the pair is
unreachable, while distance/4 returns positive_infinity.
Identity queries have distance zero and an empty path. With integer
weights, the path’s weights sum exactly to the distance. Equal-weight
ties retain the earlier selected witness.
A Temporal ATMS can map source IDs to assumption supports and use a cycle’s supports to justify a contradiction. Mutually exclusive assumption environments must be instantiated separately, or handled by a future explicitly labelled distance algorithm. Retaining all sources is essential for replay and retraction; returning one path is not an enumeration of all ATMS labels.
Precedence and interval views
For feasible Y - X bounds [Lower,Upper], can_precede(STN,X,Y)
succeeds when Upper is positive or unbounded: some schedule has X < Y.
must_precede/3 requires a positive Lower: every schedule has X < Y.
The non-strict variants use non-negative bounds. Strict self-precedence
fails, while non-strict self-precedence succeeds.
window_relation/4 classifies two marginal uncertainty envelopes, not
two events. For example, two time-points constrained to be simultaneous
can both have window [0,2]; their envelope relation is equal, but
their instants cannot strictly precede each other. Unconstrained points
with those same windows could occur in either order. Marginal envelopes
omit correlations.
window_interval(STN,Point,Interval) exports one such envelope as
i(Start,End), with finite numeric bounds and Start < End. It
fails for unbounded or singleton windows, including the singleton
reference window. It exports an uncertainty envelope, not an event
duration.
event_interval(STN,StartPoint,EndPoint,Interval) exports a concrete
event as i(Start,End). Both endpoints must have finite singleton
absolute bounds and the duration must be strictly positive. Unknown
points, invalid states, uncertain or unbounded endpoints, and reversed
or zero-duration events fail. Both exports preserve computed endpoint
numeric representations and leave the state and source identifiers
unchanged.
event_relation(STN,Start1,End1,Start2,End2,Relation) instead
requires all four endpoints to have finite singleton absolute bounds,
and each event to have positive duration. Both views jointly rank their
four endpoints by arithmetic value and delegate to interval::new/3
and interval::relation/3. Shared ranks preserve arithmetic equality,
including equality between an integer and a float, without converting
integers to floats. This avoids using the interval object’s term
ordering as numeric ordering. Ranked interval terms are internal to the
query and are not exported coordinates.
The exported i/2 descriptors contain actual numeric coordinates, not
internal ranks. They use arithmetic endpoint ordering and are plain
numeric data, not a portable replacement for the ranked interval
bridge. In particular, do not assume they can be passed directly to
term-order-based interval predicates across backends and mixed
numeric representations. Use window_relation/4 or
event_relation/6 for portable Allen comparisons.
Relationship to interval constraint networks
The intervals library already provides
interval_constraint_network for qualitative temporal reasoning. Its
network infrastructure overlaps with this library, but the two solvers
address different constraint languages:
Aspect |
Interval constraint network |
STN |
|---|---|---|
Nodes |
Symbolic intervals |
Numeric time-points |
Constraints |
Allen relation sets,
such as
|
Difference bounds, such as
|
Propagation |
Relation composition and intersection |
Numeric addition and minimum |
Contradictions |
Empty relation sets |
Negative-weight cycles |
Results |
Qualitative relations and explanations |
Numeric bounds, schedules, source-based witnesses |
Allen relation-set propagation composes the relations along a path and intersects the result with the existing pair constraint. STN closure instead adds numeric path weights and selects tighter upper bounds. Delegating STN closure to the qualitative solver would lose metric information: an Allen relation alone cannot express a specific duration, deadline, or numeric gap.
The consistency guarantees also differ. Path consistency is not a
complete satisfiability test for arbitrary disjunctive Allen networks.
In particular, interval_constraint_network::consistent/1 checks that
explicit pair relation sets are non-empty; propagation must be requested
separately. For an ordinary STN, absence of negative cycles establishes
feasibility in exact arithmetic. This library performs that check when
constructing states; stn::consistent/1 recognizes library-produced
states rather than recomputing their consistency. Floating-point
limitations still apply.
Node management, dense indexed storage, immutable updates, and
explanation bookkeeping have similar implementation patterns. These are
candidates for shared utilities, but do not make the two propagation
operations interchangeable or by themselves justify a shared solver
abstraction. Concrete Allen classification already delegates to
interval, rather than duplicating its relation algebra.
Future symbolic uncertain-event relation networks should build on
interval_constraint_network, reusing its refinement, propagation,
and explanation APIs instead of implementing another Allen
constraint-network solver inside stn. The absence of an uncertain
Allen solver noted below is a limitation of this STN library, not of the
repository as a whole.
Combining qualitative interval constraints with metric endpoint constraints would still require an explicit bridge. Independently propagating the two networks does not establish their joint consistency. The intended boundary is therefore to keep STN as the metric solver, retain its interval predicates as adapters, and investigate shared indexing or storage utilities separately.
Examples
Anchor a point to a finite window:
| ?- stn::new([t], STN0),
stn::add_constraints(STN0, [constraint(zero,t,10), constraint(t,zero,-5)], STN),
stn::bounds(STN, t, Earliest, Latest).
Earliest = 5, Latest = 10.
Export a mixed-representation numeric window:
| ?- stn::new([t], STN0),
stn::add_constraints(STN0, [constraint(zero,t,2), constraint(t,zero,-1.0)], STN),
stn::window_interval(STN, t, Interval).
Interval = i(1.0,2).
Export a fixed event’s actual numeric coordinates:
| ?- stn::new([start,end], STN0),
stn::add_constraints(STN0, [
constraint(zero,start,1.0), constraint(start,zero,-1.0),
constraint(zero,end,2), constraint(end,zero,-2)
], STN),
stn::event_interval(STN, start, end, Interval).
Interval = i(1.0,2).
Constrain A’s duration, anchor its start, and require A to end no later than B starts. The precedence edge runs from B’s start to A’s end:
| ?- stn::new([start_a,end_a,start_b,end_b], STN0),
stn::add_constraints(STN0, [
constraint(start_a,end_a,10), constraint(end_a,start_a,-5),
constraint(zero,start_a,2), constraint(start_a,zero,0),
constraint(start_b,end_a,0), constraint(zero,start_b,20)
], STN),
stn::bounds(STN, start_a, Earliest, Latest),
stn::must_precede_or_equal(STN, end_a, start_b),
stn::window_relation(STN, start_a, start_b, Relation).
Earliest = 0, Latest = 2, Relation = before.
Here before describes the start-point envelopes. B’s end remains
unbounded, and event_relation/6 would fail because the event
endpoints are not fixed. Fixing two events to [0,2] and [2,4] permits an
actual meets classification:
| ?- stn::new([sa,ea,sb,eb], STN0),
stn::add_constraints(STN0, [
constraint(zero,sa,0), constraint(sa,zero,0),
constraint(zero,ea,2), constraint(ea,zero,-2),
constraint(zero,sb,2), constraint(sb,zero,-2),
constraint(zero,eb,4), constraint(eb,zero,-4)
], STN),
stn::event_relation(STN, sa, ea, sb, eb, Relation).
Relation = meets.
Inspect a conflict without losing its source IDs:
| ?- stn::new([a,b], STN0),
stn::try_add_constraints(STN0,
[constraint(a,b,1), constraint(b,a,-2)], Ids, Outcome).
Ids = [1,2],
Outcome = inconsistent(cycle(Sources, -1)).
Sources contains constraint(1,a,b,1) and
constraint(2,b,a,-2) in closed-path order. Cycle starting points may
depend on the network’s declared node and source order. They do not
affect the conflict’s meaning.
Remove an intermediate point and retract its incident sources. The surviving direct constraint is weaker than the original path through the removed point:
| ?- stn::new([a,b,c], STN0),
stn::add_constraints(STN0, [
constraint(a,b,3), constraint(b,c,2), constraint(a,c,10)
], STN1),
stn::distance(STN1, a, c, Before),
stn::remove_time_points(STN1, [b], STN),
stn::time_points(STN, TimePoints),
stn::distance(STN, a, c, After).
Before = 5, TimePoints = [zero,a,c], After = 10.
Generate a schedule with a positive anchor and a disconnected negative edge:
| ?- stn::new([anchor,a,b], STN0),
stn::add_constraints(STN0, [
constraint(anchor,zero,-5), constraint(zero,anchor,10),
constraint(a,b,-2)
], STN),
stn::schedule(STN, Schedule).
Schedule = [time(zero,0),time(anchor,5),time(a,5),time(b,3)].
Limitations
Numeric domain and precision. Only finite integers and floats are accepted as weights. Symbolic infinities are output bounds, not admissible weights. Native numeric infinities and NaNs are rejected where supported by the backend; rational or other numeric types are not accepted. Integer computations are exact within backend arithmetic limits. Mixed numeric arithmetic and floats can lose precision through rounding, cancellation, underflow, and accumulation. This affects bounds, zero comparisons, negative-cycle detection, and witnesses. There is no implicit epsilon or exact-real guarantee for floating-point results. Prefer suitably scaled integers when conflicts must soundly justify ATMS nogoods.
Numerical diagnostics. Arithmetic evaluation, overflow, and backend representation errors propagate; they are not temporal contradictions. A non-finite computed sum raises
evaluation_error(float_overflow). Contradictory numerical diagnostics, such as a detected cycle whose reconstructed weight is not negative, a negative closure diagonal after the consistency check, a cyclic witness reconstruction, or a generated schedule violating a source inequality after normalization, raiseevaluation_error(stn_numerical_inconsistency). Float path/cycle sums can differ with evaluation order. No automatic rescaling, tolerance, numerical repair, or complete detection of floating-point inaccuracies is provided.Expressiveness. Stored constraints are closed, non-strict difference inequalities over real-valued time. No strict stored inequalities, disjunctive temporal constraints, contingent durations (STNUs), resource constraints, or optimization are provided. Strict precedence queries do not insert strict constraints. A cutoff policy and its current-time assumptions must be supplied by the caller.
Reference and unboundedness.
zerois reserved, fixed at zero, and cannot be supplied tonew/2, removed, or replaced by the caller. Points are not implicitly non-negative. Absolute bounds can be one-sided or completely unbounded; callers must handle symbolic infinities explicitly. Time-point labels must be declared, distinct, and ground. Numeric label identity differs from numeric value equality. Cyclic terms are not supported inputs.Qualitative views.
window_relation/4requires finite non-degenerate windows and describes only marginal envelopes. It cannot establish possible or entailed Allen relations between uncertain events and omits joint endpoint correlations.event_relation/6requires four finite fixed endpoints and positive durations. Both views fail for zero-duration intervals and unbounded endpoints. There is no event registry or uncertain Allen relation solver.Numeric interval exports.
window_interval/3andevent_interval/4export only finite, non-degenerate numerici/2descriptors, not internal ranks or certified term-orderedintervalvalues. Mixed integer/float coordinates must not be assumed compatible with term-order-based interval operations on every backend. These exports do not add uncertain-event relation solving, event registration, zero-duration intervals, or support for unbounded descriptors. Numeric precision limitations still apply.Schedule selection.
schedule/2returns one deterministic assignment, not all schedules, an optimal assignment, or a unique or globally earliest solution.earliest_schedule/2provides a componentwise earliest assignment only when every point has a finite lower bound; it fails otherwise rather than introducing floors or ignoring unbounded points. Its minimality guarantee is for exact arithmetic, not approximate floating-point results. Neither predicate enumerates schedules or optimizes general objectives. Times are not implicitly non-negative, and finite choices for unbounded points do not make their windows bounded. Floating-point normalization can lose differences; a failed source check raises a numerical diagnostic rather than returning an invalid assignment. Passing the check uses backend arithmetic, not exact-real certification. There is no automatic retry with another assignment, rescaling, or execution policy.Witness completeness. Only one deterministic supporting path or negative cycle is returned. Witnesses need not be minimal conflicts or minimal supports, and alternatives, all cycles, all minimal inconsistent subsets, and all minimal nogoods are not enumerated. ATMS labels, assumption mapping, and conflict minimization belong to the caller. A single merged STN cannot represent mutually exclusive environments.
Identifiers and states. Source IDs are unique only along an accepted state lineage, not across independent networks or forks. Rejected IDs can coincide with subsequent allocations from the unchanged input state. States are opaque; constructing or altering their internal terms, or assuming a stable serialization format, is unsupported.
consistent/1recognizes library-produced states; it does not recompute or certify an arbitrary hand-built graph or closure.Point deletion. Removing a time-point also retracts all its incident source constraints. It does not perform variable elimination preserving implied bounds between surviving points, which can consequently weaken or become unbounded. Re-adding a removed label does not restore its former constraints. The reference point
zerocannot be deleted.Performance and backend limits. The closure is dense, using O(n^2) cached cells plus O(m) retained sources for n time-points (including zero) and m constraints. Floyd-Warshall takes O(n^3) cell operations. This first implementation uses linear node lookup and list-based Bellman-Ford labels, yielding O(n^2 m) worst-case consistency work. Updates, source retractions, and point additions or deletions rebuild once; there is no incremental O(n^2) update guarantee. A cached pair cell is accessed in constant time after indexing, but each public call also traverses the ground state and uses linear node lookup; query cost is not constant in network size. Witness extraction is linear in path length after validation.
schedule/2scans O(n^2) cells, whileearliest_schedule/2scans O(n) reference-column cells. Both check m sources using linear label lookup. Including full state traversal, each takes O(n^2 + nm) work and O(n) temporary storage in addition to the existing state. Multiple retained snapshots increase live memory use. Matrix dimensions are subject to backend compound-arity and memory limits. Intended for small-to-medium networks, not a large-scale or latency-sensitive solver.Verification scope. Bounded exhaustive fixtures and generated tests are not proofs of correctness or exhaustive checks over all networks or floating-point behavior.